  1. Using the figure, perform resource leveling. Assumethat each task can be performed independently of the othertasks.
  2. Referring again to this figure, performresource-limited scheduling. Assume that only three workers areavailable at any given time. What is the new completion date forthe project?
  3. How do you input this into Excel?

Task 1-2 workersTask 2-1workerTask 3-0workersTask 4-2workersTask 5-1workerTask 6-3workersDay12345678910AvailableWorkers6664233433